The next common mistake that people make with project management is thinking that an underspend is OK

2
00:00:09,740 --> 00:00:11,450
and this is surprisingly common.

3
00:00:11,570 --> 00:00:16,700
Again once you've seen this you're just You'll never make this mistake again once you've seen this.

4
00:00:16,700 --> 00:00:22,190
But you know suppose that I'm a million pound project and we're halfway through and I'm supposed to

5
00:00:22,220 --> 00:00:23,880
spend five hundred thousand.

6
00:00:23,930 --> 00:00:26,220
And suppose I've only spent 400000.

7
00:00:26,360 --> 00:00:28,170
Is that good.

8
00:00:28,550 --> 00:00:29,470
And it be easy to think.

9
00:00:29,470 --> 00:00:30,900
Well yeah I'm underspending.

10
00:00:30,920 --> 00:00:34,660
You know and I'm doing it cheaper than it was meant to be done that's great.

11
00:00:34,940 --> 00:00:38,060
But of course yes I might be underspending.

12
00:00:38,090 --> 00:00:41,710
But what also might be happening is I might be late.

13
00:00:42,410 --> 00:00:49,460
And which one is more likely that the first half turned out to be cheaper than I expected or that it

14
00:00:49,460 --> 00:00:54,410
turned out to be harder than I expected and it's taken me longer and it's going to be that second one

15
00:00:54,410 --> 00:00:56,900
isn't it it's going to be that I'm behind schedule.

16
00:00:56,900 --> 00:01:01,930
So underspend usually mean lateness.

17
00:01:01,930 --> 00:01:03,830
There are so many ways to be late.

18
00:01:03,980 --> 00:01:10,250
All you need is one person off sick one person was busy on another project and something went wrong

19
00:01:10,250 --> 00:01:16,460
and had to be done a second time or there was a task that we forgot and then we had to do it.

20
00:01:16,490 --> 00:01:18,870
There were so many ways to be behind schedule.

21
00:01:18,980 --> 00:01:22,980
And it's actually really difficult for things to be cheaper than you expected.

22
00:01:23,210 --> 00:01:27,160
So under spends usually mean lateness.

23
00:01:27,170 --> 00:01:29,800
So never think in underspend is OK.

24
00:01:30,200 --> 00:01:39,420
And it's particularly tricky because if you've got an overspending and lateness those effects cancel

25
00:01:39,430 --> 00:01:39,970
out.

26
00:01:40,100 --> 00:01:44,900
So imagine if I've only done half what I should have done but it's cost me twice as much to do that

27
00:01:44,910 --> 00:01:52,370
half that's going to look bang on on the spend or more likely imagine I've only done 90 percent of what

28
00:01:52,370 --> 00:01:53,030
I should have done.

29
00:01:53,030 --> 00:01:58,830
I'm slightly behind schedule but it's overspent a little bit it's cost me 110 percent.

30
00:01:58,850 --> 00:02:02,690
So that would mean I would be pretty much bang on on the spand.

31
00:02:03,080 --> 00:02:06,940
So you've got to be really careful looking at just the spend.

32
00:02:06,950 --> 00:02:09,080
The key is to separate out the two.

33
00:02:09,270 --> 00:02:10,430
And how do you do that.

34
00:02:10,430 --> 00:02:15,170
The answer is you look at the Gantt chart because the Gantt chart shows that you've done 90 percent

35
00:02:15,170 --> 00:02:16,450
of what you should have done.

36
00:02:16,610 --> 00:02:22,310
Then you immediately know that you're behind schedule and if the spent looks OK but you've only done

37
00:02:22,310 --> 00:02:28,130
90 percent that means you've actually overspent on that 90 percent because that's taking you back to

38
00:02:28,130 --> 00:02:30,440
the spend looking OK.

39
00:02:30,560 --> 00:02:36,530
So I think you could sum this up by saying Firstly always look at the gunshot to make sense of the money

40
00:02:37,100 --> 00:02:44,090
but also if you're underspent it probably means that you're behind schedule and that's probably because

41
00:02:44,090 --> 00:02:45,960
you've had a problem of some sort.

42
00:02:46,160 --> 00:02:50,920
And that problem will mean that in the end you'll end up spending a bit more than you planned.

43
00:02:51,260 --> 00:03:00,260
So underspent means late which means there's been a problem which means overspend now overspending just

44
00:03:00,260 --> 00:03:02,020
means you've overspent.

45
00:03:02,570 --> 00:03:09,350
So underspending or overspending means that in the end you will overspend on your project.

46
00:03:09,710 --> 00:03:14,160
And the only way we can come in on budget is to come in on time as well.

47
00:03:14,420 --> 00:03:15,890
And that's you know that's difficult.

48
00:03:15,890 --> 00:03:19,050
Most projects do overspend which is why we had contingency in.

49
00:03:19,370 --> 00:03:22,410
But the great thing is the Gantt chart shows everything you need.

50
00:03:22,430 --> 00:03:26,780
You don't have to do this guesswork of well and probably late I've probably had a problem.

51
00:03:26,780 --> 00:03:31,700
If you've got a Gantt chart which you should have you could just look at that and that will tell you

52
00:03:31,880 --> 00:03:38,200
whether the underspend is really a genuine underspend or whether more likely it's because you're behind

53
00:03:38,200 --> 00:03:38,730
schedule.