1
00:00:03,920 --> 00:00:10,950
So the AP n the Association for project managers have been developing the perfect way to plan and then

2
00:00:10,950 --> 00:00:17,400
do projects for the last hundred or 150 years they've written it all down in P.N. Baalke the project

3
00:00:17,400 --> 00:00:26,670
management body of knowledge and I've simplified that down to a 12 step process just for people who

4
00:00:26,670 --> 00:00:31,280
are doing a small project or just want to get on with doing project management.

5
00:00:31,290 --> 00:00:34,850
These are the key 12 parts of the A.P.M. process.

6
00:00:34,890 --> 00:00:39,000
So if you follow this approach this project management process you should be fine.

7
00:00:39,000 --> 00:00:44,790
Your project should come in on time on budget and correct to the specification.

8
00:00:44,790 --> 00:00:48,480
Step One of the process is to define what your project is.

9
00:00:48,480 --> 00:00:50,670
Be really clear about what you are doing.

10
00:00:50,910 --> 00:00:55,650
And I think Step 1 is the biggest cause of failure for projects if you leave it a bit vague.

11
00:00:55,680 --> 00:01:00,390
There is a risk that when you deliver it people are going to say well that's not what I was imagining

12
00:01:00,390 --> 00:01:01,710
or that's not what I wanted.

13
00:01:01,740 --> 00:01:07,410
So to all agree all the stakeholders agree in writing this is what we're going to have cost quality

14
00:01:07,410 --> 00:01:08,300
and time.

15
00:01:08,310 --> 00:01:09,780
This is how much we're going to spend.

16
00:01:09,810 --> 00:01:15,440
This is what we're going to have in scope and out of scope and also how long is it going to take.

17
00:01:15,570 --> 00:01:20,100
So Step 1 define the project that's really important don't overlook that.

18
00:01:20,370 --> 00:01:25,310
Then you start on the planning steps two to eight are all about having a really good plan.

19
00:01:25,350 --> 00:01:32,100
So the first part of planning step two is to get a list of all the tasks and there is a slight question

20
00:01:32,100 --> 00:01:35,880
about how much granularity to have how small do you go.

21
00:01:35,910 --> 00:01:41,340
Do you just say I'm going to build a house or go to do the kitchen got to do the bathroom the foundations

22
00:01:41,340 --> 00:01:47,550
the roof or do you divide the kitchen down into you know the cooker and the heated floor and the lights.

23
00:01:47,610 --> 00:01:51,770
Or do you go even more detail to use and when a drill hole push the wire through.

24
00:01:52,020 --> 00:01:54,530
So there's a slight question about how detailed to go.

25
00:01:54,600 --> 00:01:59,710
But Step two is to get a list of all the tasks then.

26
00:01:59,730 --> 00:02:06,580
Step three is to estimate those tasks and there are two things to estimate the time and the money.

27
00:02:06,600 --> 00:02:11,730
So how long do we think each task will take to do and what will it cost to do.

28
00:02:11,970 --> 00:02:18,060
And just to clarify what I mean by time because there are two types of time we have to decide how many

29
00:02:18,120 --> 00:02:21,250
hours of work are involved and we've got to estimate that.

30
00:02:21,420 --> 00:02:26,110
But also the elapsed time how many weeks til it's finished.

31
00:02:26,400 --> 00:02:28,800
And those are different things.

32
00:02:28,830 --> 00:02:30,790
Sometimes people talk about DAY.

33
00:02:30,840 --> 00:02:35,580
I'm suspicious about days because if you say well it's a three day job do you mean it's three days of

34
00:02:35,580 --> 00:02:39,330
work or do you mean it's three days of elapsed time till it's finished.

35
00:02:39,330 --> 00:02:44,850
So I like to use hours of work and then weeks of elapsed time.

36
00:02:44,850 --> 00:02:50,310
So I would talk about estimating the time and the money the time is the elapsed time three weeks.

37
00:02:50,370 --> 00:02:55,180
The money is the hours of work plus other costs.

38
00:02:55,200 --> 00:02:58,870
So Step three is to do your estimating step four.

39
00:02:58,880 --> 00:03:00,890
And I'm going to show you this in a bit more detail later.

40
00:03:00,960 --> 00:03:04,070
Step forward is to work out the running order of the tasks.

41
00:03:04,080 --> 00:03:06,150
And this is usually called a network diagram.

42
00:03:06,150 --> 00:03:11,530
What order are we going to do the tasks in Step four is really the heart of your planning process.

43
00:03:11,580 --> 00:03:17,850
That's when you really decide you know are we going to risk buying a building when we haven't got a

44
00:03:17,850 --> 00:03:23,000
permit for that country or are we going to get the furniture before the manager.

45
00:03:23,010 --> 00:03:25,550
Does the manager need to have a say in the furniture.

46
00:03:25,620 --> 00:03:30,720
So Step four is where we think about the interconnections the dependencies between the tasks and we

47
00:03:30,720 --> 00:03:32,130
draw it all out in order.

48
00:03:32,130 --> 00:03:37,940
And it also tells us therefore how long the project's going to take because we can add up the times.

49
00:03:38,070 --> 00:03:45,360
So that's step four then Step Five is to speed up that diagram if necessary because if you add up all

50
00:03:45,360 --> 00:03:51,300
the tasks and it comes to too much then how do we speed it up or we can do that by overlapping some

51
00:03:51,300 --> 00:03:54,470
of the tasks or throwing money at them that kind of thing.

52
00:03:55,140 --> 00:03:58,450
Then we get to step six which is the Gantt Chart.

53
00:03:58,470 --> 00:04:00,660
Now again I'm going to talk about these more later.

54
00:04:00,660 --> 00:04:06,300
But the Gantt chart is basically a series of bars drawn out with the right length so you have you have

55
00:04:06,300 --> 00:04:08,450
a time scale on your diagram.

56
00:04:08,640 --> 00:04:14,610
And so you show each task as a bar and then you can see the whole project drawing out as a series of

57
00:04:14,610 --> 00:04:15,840
bars.

58
00:04:15,870 --> 00:04:17,660
So that's the Gantt Chart.

59
00:04:18,150 --> 00:04:24,270
Step Seven of the 12 step process is then to think about resources because if you've got several bars

60
00:04:24,270 --> 00:04:29,940
all happening at the same time you can look vertically and you can ask yourself Do we have enough resource

61
00:04:30,240 --> 00:04:33,570
to do everything that we want to do on this project.

62
00:04:33,570 --> 00:04:38,160
And we've either got to get more people or perhaps we'll have to move some of those bars later and take

63
00:04:38,160 --> 00:04:39,230
longer.

64
00:04:39,240 --> 00:04:45,330
So Step Seven is to think about the resources for your project and perhaps also for all of your projects

65
00:04:45,660 --> 00:04:48,090
because what if we've got enough for that project.

66
00:04:48,090 --> 00:04:52,680
But unfortunately at the same time as that we've got a couple of other projects happening.

67
00:04:52,920 --> 00:04:57,980
So I have a thing called the ganta of Gants where you look at all your projects and you just check that.

68
00:04:57,990 --> 00:05:01,570
Can we do all the things that we want to do in this time scale.

69
00:05:01,620 --> 00:05:03,050
So at Step 7.

70
00:05:03,210 --> 00:05:08,400
Think about the resources you need for one project and for multiple projects.

71
00:05:08,400 --> 00:05:12,690
Then the final step of the planning is Step 8 which is risk.

72
00:05:12,690 --> 00:05:16,980
So you look at your whole plan and you think what might go wrong with this project.

73
00:05:17,010 --> 00:05:18,540
How likely is it to go wrong.

74
00:05:18,540 --> 00:05:24,380
How serious would it be if it did go wrong and how can we make it less likely or less serious.

75
00:05:24,390 --> 00:05:31,250
So risk and mitigation of risk is Step 8 so that steps 2 to 8 of the 12.

76
00:05:31,410 --> 00:05:35,230
And that's the planning stage of project management.

77
00:05:35,280 --> 00:05:37,290
We then start the project.

78
00:05:37,320 --> 00:05:42,540
Remember if you're doing an gyle you plan and do plan and do plan and do but what we're doing with the

79
00:05:42,540 --> 00:05:47,610
A.P.M. process is that we plan the whole thing and then we do the whole thing.

80
00:05:48,000 --> 00:05:53,190
And you can see how there are benefits and risks of that because there is a risk we all spend ages planning

81
00:05:53,400 --> 00:05:56,570
and when you do the first bet you'll find there's something wrong with your plan.

82
00:05:56,700 --> 00:06:01,590
But if you do plan do plan do then you don't have an overall view of the project and you don't know

83
00:06:01,590 --> 00:06:02,860
how long it's going to take.

84
00:06:03,120 --> 00:06:05,850
So the A.P.M. have decided to do all the planning.

85
00:06:05,880 --> 00:06:09,110
Make sure it's right and then you carry out your plan.

86
00:06:09,810 --> 00:06:16,950
So Step 9 as you carry out your plan you monitor your progress and that's normally done by coloring

87
00:06:16,950 --> 00:06:21,510
in the Gantt chart I'm going to show you this later color in so that you can check the keeping up with

88
00:06:21,510 --> 00:06:22,430
your plan.

89
00:06:22,680 --> 00:06:28,020
And so that is Step 9 Step 10 is where you monitor the money.

90
00:06:28,110 --> 00:06:30,150
So you keep track of how much you've spent.

91
00:06:30,180 --> 00:06:35,790
And again you have to look at whether what you have spent compares favorably with what you should spend

92
00:06:35,970 --> 00:06:38,330
and if you're overspending you can work out what to do.

93
00:06:38,340 --> 00:06:42,730
Step 11 is where we adjust our plan if necessary.

94
00:06:42,730 --> 00:06:47,880
So if we are running behind or overspending at Step 11 we think right what are we going to do about

95
00:06:47,880 --> 00:06:48,810
that.

96
00:06:48,870 --> 00:06:52,500
And of course things always change doing projects.

97
00:06:52,530 --> 00:06:54,510
Sometimes it's outside factors.

98
00:06:54,600 --> 00:07:00,510
Sometimes it's the customer asking for something else but for whatever reason things change during projects

99
00:07:00,840 --> 00:07:04,620
and so step 11 is where we rejig the plan.

100
00:07:04,620 --> 00:07:10,080
And this is where agile people say are well you see you know your process isn't very flexible but actually

101
00:07:10,170 --> 00:07:14,560
it's really flexible because we know we're going to be changing the plan at Step 11.

102
00:07:14,610 --> 00:07:17,700
We've got a whole stack for that and we're absolutely fine with that.

103
00:07:17,700 --> 00:07:21,220
We know that no battle plan withstands contact with the enemy.

104
00:07:21,390 --> 00:07:28,170
But the good thing about having a plan is that if you have to change it you know the effect of the change.

105
00:07:28,170 --> 00:07:31,620
So if a customer says oh can I have an extra page on that website.

106
00:07:31,770 --> 00:07:34,880
You could say absolutely no problem at all to do that.

107
00:07:35,100 --> 00:07:38,710
But it will take a bit longer and it will cost a bit more.

108
00:07:39,210 --> 00:07:43,250
Compared to the original plan at Step 11.

109
00:07:43,860 --> 00:07:48,050
And then finally step 12 is to review the project at the end.

110
00:07:48,150 --> 00:07:49,490
What have we learnt.

111
00:07:49,950 --> 00:07:54,640
Often forgotten very important because it's really the only time that you learn.

112
00:07:54,920 --> 00:07:58,220
You know you think you'll remember for next time but will you.

113
00:07:58,290 --> 00:08:03,690
So Step 12 is where you write down everything you've learned and you store all your reviews in a folder

114
00:08:03,930 --> 00:08:09,120
so that anybody different to you who might be doing a similar project to the one you did can look in

115
00:08:09,120 --> 00:08:10,950
the folder and learn the lessons.

116
00:08:10,950 --> 00:08:16,230
So even if you've learnt it the challenges for the whole organization to learn those lessons and you

117
00:08:16,230 --> 00:08:19,630
can do that if you keep a folder of reviews.

118
00:08:20,220 --> 00:08:25,910
So that's the A.P.M. process and you can see it's four sections really is defining the project.

119
00:08:25,920 --> 00:08:30,990
It's planning the project it's monitoring the project and it's reviewing it at the end.

120
00:08:31,590 --> 00:08:35,200
So that's the ideal way that you would do your project.

121
00:08:35,250 --> 00:08:39,270
But the big question really is what tends to go wrong.
