1
00:00:06,640 --> 00:00:12,860
Chapter 11 in the Pinback guide is all about risk management and a lot of processes here in risk management.

2
00:00:12,880 --> 00:00:15,070
So make certain you know these terms.

3
00:00:15,060 --> 00:00:18,940
So here are the important terms you must know some different levels of risk.

4
00:00:18,940 --> 00:00:26,290
Remember we have individual project level individual project risk so individual risk but also the overall

5
00:00:26,290 --> 00:00:29,340
project risk the odds of the project being successful.

6
00:00:29,620 --> 00:00:36,940
Our goal and risk identification is to identify risk our goals in qualitative and quantitative analysis

7
00:00:37,270 --> 00:00:40,420
is to see what our risk exposure is.

8
00:00:40,420 --> 00:00:46,220
So one of the threats and opportunities associated with those risks that all risk are negative.

9
00:00:46,240 --> 00:00:48,360
So we could have positive risk as well.

10
00:00:49,120 --> 00:00:54,170
Some propolis this is something that seems like it could be a really good exam question.

11
00:00:54,400 --> 00:00:55,930
So you have this vodka.

12
00:00:55,960 --> 00:01:04,600
The U.S.A. is a volatile uncertain complexity or ambiguous that helps you define risk anti-cop technical

13
00:01:04,600 --> 00:01:10,300
environmental commercial operational political that makes you think about what risk would be in those

14
00:01:10,300 --> 00:01:11,120
areas.

15
00:01:11,230 --> 00:01:17,920
And Passau political economic social technological legal and environmental.

16
00:01:17,950 --> 00:01:24,280
So those are some promp list to help you think about and have the project team think about where our

17
00:01:24,280 --> 00:01:30,700
risk in the project remember our probability impact matrix of the risk probability times impact gives

18
00:01:30,700 --> 00:01:31,680
a score.

19
00:01:31,720 --> 00:01:35,760
This is qualitative using an ordinal scale.

20
00:01:35,890 --> 00:01:42,550
We do the same thing but we do this in quantitative where we really study we have evidence of that probability

21
00:01:42,970 --> 00:01:44,170
and we really study it.

22
00:01:44,170 --> 00:01:48,850
We look at the impact and that tells us our expected monetary value.

23
00:01:48,850 --> 00:01:55,690
You sum up that expected monetary value if that helps you find your contingency reserve pay attention

24
00:01:55,690 --> 00:01:58,360
that some of those impacts could be positive.

25
00:01:58,390 --> 00:02:02,960
So that could change the expected monetary value these are negative.

26
00:02:02,980 --> 00:02:10,450
But look at Risk see is positive also in risk management we talked about negative and positive responses

27
00:02:10,720 --> 00:02:17,160
so negative you could escalate it avoid it transfer it mitigate it or accept it.

28
00:02:17,500 --> 00:02:21,180
And then we had positive risk events never we had escalate.

29
00:02:21,370 --> 00:02:26,180
We have exploiting sharing and enhancing and accepting.

30
00:02:26,320 --> 00:02:27,930
So those are positive risks.

31
00:02:27,940 --> 00:02:31,200
So no those risks know the characteristics of those.

32
00:02:31,220 --> 00:02:36,730
If you need a little brush up it's Chapter 11 in the Pinback or go back and watch our course on risk

33
00:02:36,730 --> 00:02:37,720
management.

34
00:02:37,720 --> 00:02:38,740
All right great job.

35
00:02:38,830 --> 00:02:39,920
Keep moving forward.
