1
00:00:06,310 --> 00:00:12,670
When we talk about a predictive lifecycle versus an ad Jayal or adaptive lifecycle we need to go back

2
00:00:12,670 --> 00:00:18,370
and look at the idea of the triple constraints and predictive versus the agile triangle of constraints

3
00:00:18,760 --> 00:00:22,150
in a predictive scope is typically fix.

4
00:00:22,150 --> 00:00:28,630
This is what you have to create these are the requirements where in an ad Jayal the scope it varies

5
00:00:28,630 --> 00:00:36,280
because of that product backlog it can shift and priorities change time and cost typically vary in triple

6
00:00:36,280 --> 00:00:41,950
constraints with the scope remains constant time and cost and add Jayal is fixed.

7
00:00:41,950 --> 00:00:44,500
So it's considered an inverted triangle.

8
00:00:44,500 --> 00:00:48,580
When we talk about the agile trial triangle of constraints.

9
00:00:48,760 --> 00:00:54,460
So just be familiar with that idea that an agile time and cost this fix and the scope varies versus

10
00:00:54,460 --> 00:01:00,420
triple constraints where time and cost can vary in the scope should remain constant.

11
00:01:01,780 --> 00:01:04,400
The difference between the charter in the scope.

12
00:01:04,420 --> 00:01:09,490
So we go back to the idea of the charter the charter is all about the high level the project or purpose

13
00:01:09,490 --> 00:01:15,990
or justification the measurable project objectives what are the high level requirements the description

14
00:01:15,990 --> 00:01:19,720
of what's the overall project risk and our milestones.

15
00:01:19,720 --> 00:01:23,650
Do we have Pria pre-approved financial resources so how much.

16
00:01:23,650 --> 00:01:25,530
What's the summary budget here.

17
00:01:25,810 --> 00:01:29,570
Stakeholder list you have some requirements to start with.

18
00:01:29,710 --> 00:01:36,070
You have the project manager what's the roles and responsibilities for the PM and the name and authority

19
00:01:36,070 --> 00:01:37,240
of the sponsor.

20
00:01:37,240 --> 00:01:42,480
So the charter is all about authorizing the work and authorizing the project manager.

21
00:01:42,520 --> 00:01:45,760
The scope is all about what we will create.

22
00:01:45,790 --> 00:01:48,840
So we have the authority now we create it in the scope.

23
00:01:48,910 --> 00:01:51,580
So what is the project's scope description.

24
00:01:51,790 --> 00:01:53,180
What are the deliverables.

25
00:01:53,230 --> 00:01:54,160
How do we know were done.

26
00:01:54,160 --> 00:01:56,140
So what's the acceptance criteria.

27
00:01:56,280 --> 00:02:00,420
And are there any project exclusions or things that are out of scope.

28
00:02:00,460 --> 00:02:02,210
So that's very important to know.

29
00:02:02,570 --> 00:02:09,100
Another scope management process you must be familiar with is validate scope validate scope is about

30
00:02:09,310 --> 00:02:14,170
the customer receiving signing off accepting what weve created.

31
00:02:14,260 --> 00:02:21,300
It is an inspection driven process and our goal is the customer to accept the work to have formal acceptance.

32
00:02:21,550 --> 00:02:28,090
Remember this can happen at the end of a phase always at the end of a project or when you create a major

33
00:02:28,090 --> 00:02:29,030
deliverable.

34
00:02:29,110 --> 00:02:31,030
You could validate scope.

35
00:02:31,090 --> 00:02:36,100
So those are some key things you want to know from Chapter 5 in the Pinback on Scope management.
