1
00:00:04,410 --> 00:00:08,910
Another estimating approach that you can use is a three point estimate.

2
00:00:08,910 --> 00:00:12,360
And there are a couple of variations of this she'll need to know for your exam.

3
00:00:12,780 --> 00:00:20,730
A three point estimate is where we find the average of the optimistic the most likely and the pessimistic

4
00:00:21,330 --> 00:00:26,520
this thing approached a three point estimating is called a triangular distribution because we have a

5
00:00:26,520 --> 00:00:31,320
triangle of optimistic most likely and pessimistic.

6
00:00:31,320 --> 00:00:32,630
So there you go triangle.

7
00:00:32,940 --> 00:00:42,660
So in this example if we had an optimistic estimate of 25 hours or most likely 45 or pessimistic the

8
00:00:42,660 --> 00:00:51,170
worst case is 75 so we took 25 plus 45 plus 75 and then divide by three.

9
00:00:51,240 --> 00:00:54,400
It would be forty eight point three three hours.

10
00:00:54,450 --> 00:00:57,510
So that's what we would predict how long that activity would take.

11
00:00:59,510 --> 00:01:04,170
Another approach is a perch technique it's also a three point estimate.

12
00:01:04,170 --> 00:01:08,340
And this is called beta distributions so it's a little different.

13
00:01:08,390 --> 00:01:14,540
Pert means program evaluation and review technique but we just call it what it does.

14
00:01:14,540 --> 00:01:22,310
It's weighted towards the most likely where the trained gular it was just an average person has a little

15
00:01:22,460 --> 00:01:26,000
little weight or weight it factor for most likely.

16
00:01:26,000 --> 00:01:34,400
So what we're doing here we take optimistic plus four times the most likely plus pessimistic divided

17
00:01:34,400 --> 00:01:38,090
by six and that will equal our estimate.

18
00:01:38,090 --> 00:01:44,440
So we'll take the same case here 25 45 and 75.

19
00:01:44,510 --> 00:01:51,590
So we take four times 45 plus 25 plus 75 or whatever that comes out to be.

20
00:01:51,610 --> 00:01:57,040
We divide by six and then we would say it's forty six point six six hours.

21
00:01:57,290 --> 00:02:03,080
We're weighted meaning that we're putting more belief in the most likely time.

22
00:02:03,100 --> 00:02:10,390
So this is called a beta distribution it's a beta of our X factor towards the middle.

23
00:02:10,450 --> 00:02:11,910
Beta distribution.

24
00:02:13,060 --> 00:02:17,590
3. estimates You might also see them abreviated like this on your exam.

25
00:02:17,590 --> 00:02:24,430
Don't let it worry you don't let it throw you where most likely might be a t in an optimistic t and

26
00:02:24,500 --> 00:02:27,610
no I'm pessimistic t it p.

27
00:02:27,850 --> 00:02:29,560
And then a three point estimate.

28
00:02:29,590 --> 00:02:30,730
A T.

29
00:02:30,970 --> 00:02:32,020
Uppercase e.

30
00:02:32,080 --> 00:02:37,850
And then you can see the little T there preceding all of our factors that just means time.

31
00:02:38,410 --> 00:02:39,910
So a little hint.

32
00:02:39,910 --> 00:02:42,430
You can also do this with cost.

33
00:02:42,430 --> 00:02:45,710
So instead of a T you might see a little scene there.

34
00:02:45,760 --> 00:02:49,400
And so the C would be it's a cost with a three point estimate.

35
00:02:49,450 --> 00:02:51,880
And we'll see that in chapter 7.

36
00:02:51,880 --> 00:02:55,570
Let's compare and contrast here.

37
00:02:55,600 --> 00:03:03,590
All right so we have an optimistic of 40 hours most likely 55 pessimistic at 70.

38
00:03:03,820 --> 00:03:06,120
So what happens if we do it with perked.

39
00:03:06,270 --> 00:03:09,010
And what will happen if we do it with our three point estimate.

40
00:03:09,010 --> 00:03:10,850
So what will the results be.

41
00:03:10,870 --> 00:03:13,460
So let's take a look at our formulas.

42
00:03:13,480 --> 00:03:25,520
So our total for the three point estimate if we take 40 plus 55 plus 90 is 185 divided by three 61 points

43
00:03:25,600 --> 00:03:28,220
point seven that's our average amount of time.

44
00:03:28,220 --> 00:03:31,600
That's what we would predict if we use pert.

45
00:03:31,900 --> 00:03:41,730
It's 40 plus 55 plus 90 and you could see our formula 40 plus four times 55 plus 90 divided by six.

46
00:03:41,950 --> 00:03:45,230
So you see some of those up divide by six.

47
00:03:45,250 --> 00:03:47,920
And the answer would be fifty eight point three.

48
00:03:48,220 --> 00:03:52,800
So what's happening here is with a three point it's just the average.

49
00:03:52,990 --> 00:04:01,870
So if you have a very negative pessimistic or a really aggressive optimistic estimate it will skew your

50
00:04:01,870 --> 00:04:08,520
average in per everything is skewed if you will or weighted towards most likely.

51
00:04:08,560 --> 00:04:13,410
So you have to have a lot of confidence in your most likely estimate.

52
00:04:13,660 --> 00:04:18,730
You do this for every single activity to do three point or per.

53
00:04:19,030 --> 00:04:23,020
The reality is you could take just some of your activities and do this.

54
00:04:23,020 --> 00:04:26,800
But for your exam it's used to the whole project.

55
00:04:26,800 --> 00:04:29,890
So that's pert and three point estimate.

56
00:04:29,890 --> 00:04:34,160
So know how to do those you're probably going to have to do that math on your exam.

57
00:04:34,510 --> 00:04:35,080
All right.

58
00:04:35,170 --> 00:04:36,240
Keep moving forward.

59
00:04:36,310 --> 00:04:38,460
I'll see you in the next lecture.
