1
00:00:04,870 --> 00:00:11,170
Now that we've talked about the relationship between activities we can get in and begin creating a network

2
00:00:11,170 --> 00:00:17,650
diagram so to create a network diagram we're talking about visualizing the project work we're talking

3
00:00:17,650 --> 00:00:19,860
about the flow of the project work.

4
00:00:20,050 --> 00:00:26,380
So we're showing the relationship of our work activities and how the project flows from the start to

5
00:00:26,380 --> 00:00:34,360
the end the only type of network diagram you need to know where your exam is called activity on Node

6
00:00:34,400 --> 00:00:34,870
8.

7
00:00:34,960 --> 00:00:41,150
In like in this little picture here activity see Indiani That's an activity.

8
00:00:41,150 --> 00:00:44,070
And so the arrows just show the flow.

9
00:00:44,230 --> 00:00:48,460
The nodes are where all the information is about the activity.

10
00:00:48,760 --> 00:00:55,030
What we use and what you'll be using and Eithan over here exam is called the precedence diagramming

11
00:00:55,030 --> 00:01:02,470
method the precedence diagramming method is like we saw with with our relationship between activities

12
00:01:02,950 --> 00:01:06,430
we have successors and predecessors.

13
00:01:06,670 --> 00:01:12,370
So predecessors are upstream successors or downstream.

14
00:01:12,370 --> 00:01:15,440
It's the most common it's what Microsoft Project uses.

15
00:01:15,610 --> 00:01:21,190
If you were to draw out the flow of your work like you start here and you end up here in the flow of

16
00:01:21,190 --> 00:01:24,040
all your activities you'll be using PTM.

17
00:01:24,070 --> 00:01:33,900
So what's the predecessor and a successor each activity can be a predecessor and a successor.

18
00:01:34,150 --> 00:01:37,950
So you can have an activity to prime the wall.

19
00:01:38,110 --> 00:01:44,620
While this could be a successor to install the drywall you have to put the drywall up first then you

20
00:01:44,620 --> 00:01:49,180
can prime the wall so it succeeds the drywall.

21
00:01:49,290 --> 00:01:51,590
What after this.

22
00:01:51,760 --> 00:01:55,270
Any activity after this would succeed this guy.

23
00:01:55,270 --> 00:01:57,980
So this could be paint the wall.

24
00:01:58,120 --> 00:02:05,360
So paint the wall is now a successor and this guy in this instance is a predecessor so don't let that.

25
00:02:05,380 --> 00:02:06,610
Don't let that tricky.

26
00:02:06,610 --> 00:02:08,650
That it can only be one or the other.

27
00:02:08,650 --> 00:02:14,320
So an activity could be both because you could have predecessors and successors.

28
00:02:14,320 --> 00:02:16,350
The activities are put in little square.

29
00:02:16,360 --> 00:02:17,510
These are the nodes.

30
00:02:17,620 --> 00:02:21,860
You might sometimes see them in a circle but squares are the most common.

31
00:02:22,180 --> 00:02:25,000
And then the arrows that you'll see in this.

32
00:02:25,000 --> 00:02:31,060
Let's take a look now the arrows that you see or the connection of the lines that you see are just show

33
00:02:31,060 --> 00:02:32,370
the flow of the work.

34
00:02:32,410 --> 00:02:37,540
So sometimes you don't see an arrow and other times you will don't let that trick you it's just the

35
00:02:37,540 --> 00:02:42,600
flow of the work the the lines show how the work flows.

36
00:02:42,610 --> 00:02:48,190
So in this example we're seeing these different nodes and we're seeing a lot of different numbers.

37
00:02:48,250 --> 00:02:51,220
So we're moving closer to a scheduled network analysis.

38
00:02:51,220 --> 00:02:57,070
I know that's what a lot of you are eager to see but this is our six our sample network diagram.

39
00:02:57,070 --> 00:03:02,180
This is a schedule model of how do we go from the start all the way to the end.

40
00:03:02,350 --> 00:03:05,380
And so we'll see this in more detail we're getting there.

41
00:03:05,410 --> 00:03:08,670
We're going to figure out how do we find float.

42
00:03:08,680 --> 00:03:09,750
This is how we do.

43
00:03:09,760 --> 00:03:14,450
This is what we base it on is you have to have a network diagram to examine.

44
00:03:14,740 --> 00:03:15,480
So hang tight.

45
00:03:15,490 --> 00:03:16,570
We're getting there.

46
00:03:16,660 --> 00:03:17,370
It's coming.

47
00:03:18,950 --> 00:03:21,490
Network templates just like our activity list.

48
00:03:21,530 --> 00:03:24,060
There's no reason to start from scratch every time.

49
00:03:24,230 --> 00:03:27,930
So if I have a similar project let's just adapt it.

50
00:03:27,980 --> 00:03:33,440
If you always have the same flow of works or nearly the same flow of work you can have a pre-populated

51
00:03:33,440 --> 00:03:36,020
network diagram that you just adapt.

52
00:03:36,020 --> 00:03:40,160
So again this is an organizational process asset.

53
00:03:40,460 --> 00:03:48,190
Keep moving forward.
