1
00:00:04,880 --> 00:00:11,900
Once we have the project management plan created in particular the schedule management plan the subsidy

2
00:00:11,900 --> 00:00:12,660
plan.

3
00:00:12,890 --> 00:00:15,630
Then we can go about defining activities.

4
00:00:15,890 --> 00:00:22,580
This is to create the activities list all of the activities that we have to do in order for the scope

5
00:00:22,580 --> 00:00:24,090
to be complete.

6
00:00:24,110 --> 00:00:30,080
So to define activities we're talking about taking our work break down structure and the smallest item

7
00:00:30,080 --> 00:00:32,710
in the WB is a work package.

8
00:00:32,850 --> 00:00:39,820
We're correlating that work package to the activities that are needed in order to create the work package.

9
00:00:39,830 --> 00:00:41,560
So I need the WTS.

10
00:00:41,780 --> 00:00:48,860
I'm going to rely on the decomposition of scope to identify the work package and that allows me then

11
00:00:48,860 --> 00:00:55,760
to create the activity list the activity list is really needed because it helps me estimate what I'm

12
00:00:55,760 --> 00:00:56,900
going to schedule.

13
00:00:57,020 --> 00:01:05,090
And also to control the work along with our activities will define what are the activity attributes

14
00:01:05,270 --> 00:01:10,380
so that each activity will have different attributes or characteristics that we want to be aware of.

15
00:01:11,120 --> 00:01:17,030
The milestone list shows all of the activities that lead up to creating that milestone.

16
00:01:17,240 --> 00:01:23,990
So recall typically at the end of a phase we get a milestone or do you have a key deliverable in your

17
00:01:23,990 --> 00:01:24,690
project.

18
00:01:24,770 --> 00:01:28,040
That's a milestone as far as activities go.

19
00:01:28,100 --> 00:01:32,900
We can see the activities that are needed in order to create that milestone.

20
00:01:33,380 --> 00:01:36,180
Let's look at the Ito's for the activity list.

21
00:01:36,500 --> 00:01:42,530
Our inputs the implant in particular the schedule management plan and the scope baseline.

22
00:01:42,620 --> 00:01:49,980
Maybe the scope baseline scope statement the work breakdown structure and the WTS dictionary and then

23
00:01:49,980 --> 00:01:54,270
we'll have E.F an opiate some tools and techniques here.

24
00:01:54,270 --> 00:02:00,500
Expert judgment composition rolling wave planning and meetings.

25
00:02:00,840 --> 00:02:06,630
Our outputs will be the activity list the activity attributes that milestone list we were just talking

26
00:02:06,630 --> 00:02:07,260
about.

27
00:02:07,560 --> 00:02:13,680
You could have change request we might have updates to the project management plan in particular your

28
00:02:13,680 --> 00:02:21,460
schedule baseline and your cost base line could be an output here to fighting the project activity so

29
00:02:21,460 --> 00:02:25,140
the project work and project manager work.

30
00:02:25,210 --> 00:02:26,700
So there's a difference here.

31
00:02:26,740 --> 00:02:33,310
The project work we're talking about the activities that will create the project scope the project manager

32
00:02:33,310 --> 00:02:40,690
work sometimes called L.E. level of effort are the activities that you have to do in order to manage

33
00:02:40,690 --> 00:02:41,640
the project.

34
00:02:41,800 --> 00:02:51,800
So quality control of the inspection the creation of a report that's p m word planning is P word.

35
00:02:52,080 --> 00:03:00,240
While those are needed they don't necessarily contribute to the creation of the project scope but often

36
00:03:00,240 --> 00:03:04,330
we still need to schedule those activities to make certain they happen.

37
00:03:04,350 --> 00:03:11,310
So you might schedule of quality control inspection after key deliverables or you might schedule when

38
00:03:11,310 --> 00:03:17,890
reports are to happen on a regular basis or when meetings happen on a regular basis in your project.

39
00:03:17,910 --> 00:03:24,570
So that's project management work that doesn't necessarily contribute to the scope the creation of the

40
00:03:24,570 --> 00:03:25,680
product scope.

41
00:03:27,240 --> 00:03:28,880
Other planning processes.

42
00:03:28,910 --> 00:03:35,820
So you think about in each one of our knowledge areas that takes time to play and see think about scope

43
00:03:35,910 --> 00:03:44,280
and cost quality planning for H.R. communications planning in risk we'll spend a lot of time in risk

44
00:03:44,280 --> 00:03:50,510
planning and then in procurement You may have some planning issues there in stakeholder engagement and

45
00:03:50,520 --> 00:03:51,870
planning is iterative.

46
00:03:51,870 --> 00:03:57,150
So you're never really done with planning until you finally go into closing.

47
00:03:57,150 --> 00:04:00,660
What about the procurement time and the sequence of activities.

48
00:04:00,930 --> 00:04:06,070
So the sequence of activities we're talking about what order should these happen.

49
00:04:06,660 --> 00:04:12,960
So that helps us to create the schedule or at least the flow of the work the procurement time we have

50
00:04:12,960 --> 00:04:17,050
to consider the lead time to purchase something.

51
00:04:17,070 --> 00:04:25,230
So I need these cabinets installed in 40 days from now procurement takes 30 days for it to happen to

52
00:04:25,230 --> 00:04:27,220
get the materials on site.

53
00:04:27,270 --> 00:04:36,300
So I have to think about 30 days from now I need the cabinets so that affects my schedule internal and

54
00:04:36,300 --> 00:04:42,810
external events so internal events could be things like resource availability company holidays where

55
00:04:42,810 --> 00:04:47,120
resources are used in other projects or somebody is taking a vacation.

56
00:04:47,160 --> 00:04:55,560
External events the weather laws and regulations the vendor has an issue with getting the materials.

57
00:04:55,560 --> 00:05:03,030
Those are really outside of your control known and unknown events known events we're talking about risk

58
00:05:03,090 --> 00:05:06,040
that I know these things are going to happen.

59
00:05:06,180 --> 00:05:08,040
Unknown's are you know.

60
00:05:08,040 --> 00:05:14,700
No one knows that a project team member could quit in the middle of your project or the project could

61
00:05:14,700 --> 00:05:15,850
get cancelled.

62
00:05:15,870 --> 00:05:21,230
They may not have the money to put in to the project to continue to fund it.

63
00:05:21,330 --> 00:05:26,810
So unknown events can obviously wreck your schedule.

64
00:05:27,050 --> 00:05:33,200
The decomposition of project activities we're talking about taking the work packages and the WTS and

65
00:05:33,200 --> 00:05:38,990
then breaking those down into the work the activities to create the work packages.

66
00:05:39,270 --> 00:05:47,030
So in theory if we do the activities we're creating the work packages if we complete all of the work

67
00:05:47,030 --> 00:05:51,680
packages then we're completing that deliverable in the WTS.

68
00:05:51,680 --> 00:05:58,650
If we create all the WB deliverables then we have satisfied the project scope to satisfy the project

69
00:05:58,650 --> 00:05:59,450
scope.

70
00:05:59,450 --> 00:06:02,940
You've met the product scope and then your project is accepted.

71
00:06:03,080 --> 00:06:06,680
So that's kind of the roll up of activities here.

72
00:06:06,740 --> 00:06:11,060
There's a little rule you ought to be familiar with called the 880 rule.

73
00:06:11,480 --> 00:06:17,450
When we decompose the work break down structure we don't want to get so granular that we just keep breaking

74
00:06:17,450 --> 00:06:23,660
things down or breaking things down all the way down to the screw that goes into a cabinet.

75
00:06:23,660 --> 00:06:32,000
We want to use a general rule here it's called a heuristic that we say between eight hours in 80 hours

76
00:06:32,270 --> 00:06:36,230
that's how long each word package should take to create.

77
00:06:36,260 --> 00:06:41,480
So if it's you know installing a door knob All right that might take two hours.

78
00:06:41,480 --> 00:06:45,740
That's a little too granular might just say install the door.

79
00:06:45,740 --> 00:06:47,300
Well that might be four hours.

80
00:06:47,360 --> 00:06:52,590
So you might say install all the doors or complete the finishing for each room.

81
00:06:52,610 --> 00:06:56,830
So it's just a way of sizing the work that needs to be done.

82
00:06:57,050 --> 00:06:59,820
It's a general rule sometimes you might want to be very clear.

83
00:06:59,930 --> 00:07:05,150
We need a door a special door that's going to go into the laundry room.

84
00:07:05,180 --> 00:07:08,370
All right so the 80 rules just heuristic.

85
00:07:08,420 --> 00:07:12,360
So anything less than eight hours in your activity list is too small.

86
00:07:12,560 --> 00:07:15,960
Anything greater than 80 hours though is too big.

87
00:07:16,010 --> 00:07:22,800
So it's just try to stay in that window between eight and 80 hours decomposed to project activities

88
00:07:22,830 --> 00:07:28,430
three inputs that we really need the scope baseline because we're talking about the WTS.

89
00:07:28,470 --> 00:07:34,620
And that would be a dictionary and a scope statement enterprise environmental factors at O.P..

90
00:07:34,950 --> 00:07:39,230
Those are all things that we need to decompose project activities.

91
00:07:40,960 --> 00:07:43,000
Some other planning components to consider.

92
00:07:43,000 --> 00:07:46,390
We have control accounts in planning packages.

93
00:07:46,390 --> 00:07:52,180
I talked a little bit about this way back in the scope management lets just have a clear definition

94
00:07:52,180 --> 00:07:56,440
here a control account or a control account plan.

95
00:07:56,470 --> 00:08:00,120
It's like a little marker in your WPX.

96
00:08:00,280 --> 00:08:02,460
So recall that I'm building a house for you.

97
00:08:02,590 --> 00:08:10,820
And in this example we know we need a kitchen I don't need to know everything today for the kitchen

98
00:08:10,820 --> 00:08:17,500
deliverable but I know that we need a kitchen and that kitchen is going to have a budget of 75000.

99
00:08:17,690 --> 00:08:21,870
And most kitchens take us about a month to complete everything.

100
00:08:21,920 --> 00:08:30,260
So 75000 and about a month of labor not saying just one contiguous that much labor equates to 30 days.

101
00:08:31,850 --> 00:08:38,360
Well you have to make decisions about what goes in to the kitchen and we have $75000.

102
00:08:38,360 --> 00:08:43,820
So you have to decide what are the appliances What's the countertop What's the cabinets you are like

103
00:08:44,270 --> 00:08:45,550
what's the flooring.

104
00:08:45,620 --> 00:08:52,680
That's all part of the kitchen all of those decisions our planning packages.

105
00:08:52,700 --> 00:08:57,440
So planning packages as you say well I want this countertop and these are going to it's going to cost

106
00:08:57,440 --> 00:08:58,840
$10000.

107
00:08:59,150 --> 00:09:02,080
Well that planning package is now worth 10000.

108
00:09:02,300 --> 00:09:10,940
And we have 75000 So you have 65000 left to make decisions on appliances and counters on the flooring

109
00:09:10,940 --> 00:09:11,870
and so on.

110
00:09:12,140 --> 00:09:18,920
So it's the some accountability in that control account plan based on your choices will determine how

111
00:09:18,920 --> 00:09:24,190
we consume the budget and the time to actually make that happen.

112
00:09:24,620 --> 00:09:29,450
Now there can be some issues that happen here with planning components.

113
00:09:29,450 --> 00:09:35,840
For example we have to know what type of countertops you want by December 1.

114
00:09:35,870 --> 00:09:41,810
So if you don't tell me by December 1 then we're going to be late because I didn't know do you want

115
00:09:41,810 --> 00:09:45,710
a marble doing granite up poured concrete.

116
00:09:45,710 --> 00:09:49,660
You know what's the material of the type of countertops that you want.

117
00:09:49,730 --> 00:09:51,740
And we have to know by December 1.

118
00:09:51,780 --> 00:09:52,600
So you have deadlines.

119
00:09:52,610 --> 00:09:57,120
If you missed the deadline and the decision then some of your choices might go away.

120
00:09:57,150 --> 00:09:58,220
Right you've missed the deadline.

121
00:09:58,220 --> 00:10:00,550
You can't do marble Now that takes too long.

122
00:10:00,560 --> 00:10:05,630
So now you have to choose you know one of these choices or it could just be an issue it's going to push

123
00:10:05,630 --> 00:10:06,800
the project.

124
00:10:06,800 --> 00:10:10,570
So those are planning components that affect scheduling.

125
00:10:10,580 --> 00:10:11,630
Great job.

126
00:10:11,630 --> 00:10:13,120
Keep moving forward.
