1
00:00:04,510 --> 00:00:08,380
We're still working away here in Project Integration Management.

2
00:00:08,380 --> 00:00:13,780
The good news this is the last process we have to talk about in this knowledge area.

3
00:00:13,780 --> 00:00:19,330
This is also the largest knowledge area so I know you invested a lot of time in this chapter.

4
00:00:19,330 --> 00:00:25,480
Let's talk about closing the project or phase to close the project or phase we're talking about the

5
00:00:25,480 --> 00:00:27,270
whole project is done.

6
00:00:27,340 --> 00:00:32,980
Remember at the end of each phase we could do closing but we could also be closing out a contract so

7
00:00:32,980 --> 00:00:34,960
that's a closing activity.

8
00:00:34,960 --> 00:00:42,280
Let's look at our egos here to close the project or phase so to close out the project or phase our inputs.

9
00:00:42,280 --> 00:00:48,280
We need to charter the project management plan and a whole bunch of project documents the assumption

10
00:00:48,280 --> 00:00:56,800
log your basis of estimates change log issue log Lessons Learned register your milestone list your communications

11
00:00:57,270 --> 00:01:04,180
the QC measurements the different quality reports requirements documentation the Risk Report The risk

12
00:01:04,180 --> 00:01:10,120
register so a lot of businesses going into closing out the project or phase because I need that stuff

13
00:01:10,570 --> 00:01:16,700
to create the final report and to confirm that everything's been done according to plan and everything's

14
00:01:16,720 --> 00:01:24,070
closed out I'll have accepted deliverables and business documents the business case and the benefits

15
00:01:24,070 --> 00:01:30,280
management plan tools and techniques we've seen all of these already expert judgment different types

16
00:01:30,280 --> 00:01:36,520
of data analysis the new one we have here is regression analysis we'll talk about that coming up and

17
00:01:36,520 --> 00:01:44,380
then meetings outputs of close to project or phase you have lessons learned register the actual product

18
00:01:44,410 --> 00:01:53,200
the final product product service or result transition the actual final report and then OPI updates

19
00:01:53,230 --> 00:02:01,210
because what you create now becomes part of Opie a administrative closure this is a term that describes

20
00:02:02,220 --> 00:02:07,240
to the confirmation that all of your documents and deliverables are current.

21
00:02:07,540 --> 00:02:12,640
So that's the first part of the Ministry of closure this is the actual process I should say of how you

22
00:02:12,640 --> 00:02:20,530
close out the project now administrative closure is not a process one of forty nine processes but it's

23
00:02:20,530 --> 00:02:26,120
really the execution of closing the project or phase it's how you officially closed down the busy work

24
00:02:26,410 --> 00:02:33,220
of closing down a project making sure that all your issues are resolved and then all of your deliverables

25
00:02:33,220 --> 00:02:39,190
they've signed off on their formally accepted and that all of the cost you want to gather all the cost

26
00:02:39,190 --> 00:02:45,840
make sure all the costs are charged the projects you can close out the project financially administrative

27
00:02:45,840 --> 00:02:51,780
closure is all about closing all your project accounts so all those different accounts different vendors

28
00:02:51,780 --> 00:02:57,900
that everyone's paid or invoices or purchase orders all of that has to be done financial closure your

29
00:02:57,900 --> 00:03:03,360
personnel on the team they're no longer needed because we're closing down the project so they're reassigned

30
00:03:03,360 --> 00:03:10,330
to other projects so they go back to operations or whatever the case may be you might have access project

31
00:03:10,330 --> 00:03:17,080
materials so you're in construction and you've had some backup material or you have some some spare

32
00:03:17,080 --> 00:03:21,850
parts or whatever the case may be what do you do with that how do you get that into inventory or can

33
00:03:21,850 --> 00:03:26,600
you send it back to the vendor for a refund or can another project utilize it.

34
00:03:26,650 --> 00:03:30,520
So what do you do with that excess material you've got to put it somewhere you can't just ignore it

35
00:03:31,360 --> 00:03:36,820
and then reallocating any facilities or equipment so a way in your organization of saying All right

36
00:03:36,850 --> 00:03:42,850
we're no longer using this piece of equipment it's open if somebody wants to use it and then creating

37
00:03:42,850 --> 00:03:47,550
your final project report redefined What's the project successful or not.

38
00:03:49,120 --> 00:03:55,840
Throughout the project you can do closing when it comes to contract closure so you close out your contractual

39
00:03:55,840 --> 00:04:02,080
agreements it just you know a formal way of saying both parties kept up their end of the bargain here.

40
00:04:02,080 --> 00:04:09,820
If you do have any claims you have to finalize open claims so a claim is a disagreement about who's

41
00:04:09,820 --> 00:04:14,830
in the wrong here where you tell the vendor you don't think this is of quality and the vendor saying

42
00:04:14,860 --> 00:04:17,010
hey it's exactly what you asked for.

43
00:04:17,050 --> 00:04:20,050
So pay us you're like I'm not paying you oh yes they are.

44
00:04:20,050 --> 00:04:22,810
So you had this back and forth and it's no fun for anyone.

45
00:04:23,350 --> 00:04:30,310
So you have to finalize those claims as part of contractual closure if everything goes smoothly which

46
00:04:30,310 --> 00:04:35,320
most of time I think it does or might be some small claims here and there are issues here and there

47
00:04:35,320 --> 00:04:42,340
to resolve but you update your records to reflect the results and then you archive that contract administration

48
00:04:42,670 --> 00:04:44,150
for future usage.

49
00:04:44,230 --> 00:04:49,030
So that helps you in the future say oh I've got a I want to work with this vendor before or you want

50
00:04:49,030 --> 00:04:51,200
to stay away from that vendor and here's why.

51
00:04:51,220 --> 00:04:53,350
So you archive that information.

52
00:04:53,380 --> 00:04:57,670
It's called the procurement file and we'll see that in chapter 12 in the.

53
00:04:57,960 --> 00:04:59,190
A long way from now.

54
00:04:59,200 --> 00:04:59,410
Right.

55
00:04:59,410 --> 00:05:02,430
We're here in chapter four.

56
00:05:02,860 --> 00:05:06,350
Some things that you do in closing you have to create a final report.

57
00:05:06,400 --> 00:05:09,640
You could do this for the whole project or each phase.

58
00:05:09,640 --> 00:05:16,990
You may have to audit the project or the phase was it successful it was it a failure and upfront I remember

59
00:05:16,990 --> 00:05:23,870
in our benefits management plan in our charter in our scope we set the criteria for success.

60
00:05:23,890 --> 00:05:28,180
So that's what we're measuring against manage knowledge it continues on.

61
00:05:28,180 --> 00:05:31,000
How do you share that or transfer that knowledge.

62
00:05:31,000 --> 00:05:34,720
So this thing you've created it's going to go into operational transfer.

63
00:05:34,720 --> 00:05:38,620
They need some training or instruction or communication about it.

64
00:05:38,620 --> 00:05:45,640
We're going to complete lessons learned and then archive that project information some other closing

65
00:05:45,640 --> 00:05:46,320
activities.

66
00:05:46,330 --> 00:05:53,380
You've got to transfer the product service or results in to the next phase into productions or into

67
00:05:53,380 --> 00:05:54,190
operations.

68
00:05:54,190 --> 00:05:57,880
So whatever you create somebody's got to take it known and be responsible for it.

69
00:05:57,880 --> 00:06:04,660
Now we'll also finalize any suggestions for improvement so anything in the project we could have done

70
00:06:04,660 --> 00:06:08,560
better and anything in the organization that would have worked better.

71
00:06:08,560 --> 00:06:13,410
So some of these policies you might realize are kind of outdated or not very useful.

72
00:06:13,420 --> 00:06:16,950
So can you make some recommendations here.

73
00:06:17,200 --> 00:06:21,010
Sending in those suggestions on to the appropriate organizational unit.

74
00:06:21,030 --> 00:06:27,970
So H.R. your PMO whatever department you're working with and you want to measure stakeholder satisfaction

75
00:06:27,970 --> 00:06:31,210
make certain that people are happy with what you've created.

76
00:06:31,240 --> 00:06:35,540
So how do you measure that and quantify happiness.

77
00:06:35,540 --> 00:06:43,190
So you need some surveys and interviews and things of that nature in some instances people are not happy

78
00:06:43,450 --> 00:06:50,870
and the project's been terminated so early project closure project was not doing well on time or cost.

79
00:06:50,890 --> 00:06:52,470
So it was canceled.

80
00:06:52,490 --> 00:06:57,250
So when you have a project that's terminated you just don't walk away from it.

81
00:06:57,260 --> 00:06:59,400
We still have to do some closing here.

82
00:06:59,450 --> 00:07:01,150
So why was it terminated.

83
00:07:01,160 --> 00:07:02,380
Maybe it wasn't a bad thing.

84
00:07:02,380 --> 00:07:08,480
Maybe there was a new technology or that you made a realization that this wasn't feasible so you're

85
00:07:08,480 --> 00:07:10,090
going to save time and money.

86
00:07:10,140 --> 00:07:13,550
It's not always a bad thing when a project gets canceled.

87
00:07:13,760 --> 00:07:18,740
Often it is though you have to talk to the stakeholders and to go ahead and complete as many project

88
00:07:18,740 --> 00:07:24,770
closure activities that you can do like ensuring that all of the payments have been made ensuring that

89
00:07:24,770 --> 00:07:29,000
the access materials have been accounted for and are released.

90
00:07:29,000 --> 00:07:31,370
Any resources that you reserved are released.

91
00:07:31,520 --> 00:07:36,860
So you've got to make sure that everything's closed down so other people can use those resources and

92
00:07:36,860 --> 00:07:39,000
materials and so on.

93
00:07:39,530 --> 00:07:45,620
You do create a project final report even if the projects terminated early and when the project successful

94
00:07:46,010 --> 00:07:51,560
you have this final project report and it's basically a summation of what happened in the whole project

95
00:07:51,890 --> 00:07:58,160
or in that phase it defines what was met and then what about quality and any variances.

96
00:07:58,160 --> 00:08:02,890
So what happened there and was it of quality and acceptable with some variances.

97
00:08:03,140 --> 00:08:04,820
What about cost than time.

98
00:08:04,880 --> 00:08:10,640
So are there any variances with cost or schedule any variances here.

99
00:08:10,820 --> 00:08:12,260
What about the validation.

100
00:08:12,290 --> 00:08:17,690
So the customer signs off on it that you have the final product and they accept it and it's goods you

101
00:08:17,690 --> 00:08:19,590
need to sign off.

102
00:08:19,790 --> 00:08:25,730
You may have to talk about did the project meet or fail meeting the business objectives.

103
00:08:25,730 --> 00:08:26,490
That's no good.

104
00:08:26,490 --> 00:08:32,760
If you have business value or cost right to control or the schedule is way too long.

105
00:08:32,780 --> 00:08:34,330
That affects business value.

106
00:08:34,880 --> 00:08:41,150
And what about the risk in the project where those handled appropriately and how were they closed out

107
00:08:41,150 --> 00:08:43,370
and what can you learn from that.

108
00:08:43,380 --> 00:08:46,070
All right a lot of information here when it comes to closing.

109
00:08:46,110 --> 00:08:49,790
Remember you can close the project and you can close the face.

110
00:08:49,920 --> 00:08:50,460
Great job.
