1
00:00:06,960 --> 00:00:12,030
Now let's talk about some actions that you'll have to take as a project manager.

2
00:00:12,030 --> 00:00:14,230
First off we have corrective action.

3
00:00:14,250 --> 00:00:16,900
This is where you're fixing a problem.

4
00:00:16,980 --> 00:00:23,100
So you're realigning the project performance preventive action is where you don't want to make the mistake

5
00:00:23,100 --> 00:00:23,630
again.

6
00:00:23,630 --> 00:00:27,150
So you are insuring future performance.

7
00:00:27,360 --> 00:00:33,360
Now corrective action and preventive action can go hand-in-hand and then it ties in with our next action

8
00:00:33,360 --> 00:00:35,700
here which is defect repair.

9
00:00:35,700 --> 00:00:37,520
So let me give you an example.

10
00:00:37,620 --> 00:00:45,330
We have a thousand dollars to install in a building and we have four or five different groups of people

11
00:00:45,330 --> 00:00:47,540
that are going out installing these doors.

12
00:00:47,790 --> 00:00:51,370
Well we do some inspections so some quality control.

13
00:00:51,630 --> 00:00:59,760
And we notice that about 50 of the 300 doors we've installed so far are installed incorrectly.

14
00:00:59,760 --> 00:01:06,600
So we need to do corrective action which is also defect repair that we're fixing the problem or modifying

15
00:01:06,600 --> 00:01:10,250
that nonconformists the doors aren't installed properly.

16
00:01:10,310 --> 00:01:15,890
What we also do is we bring everyone together when we do a little bit of training so that we ensure

17
00:01:15,900 --> 00:01:21,870
future performance so that everyone is installing the doors correctly from this point forward.

18
00:01:22,500 --> 00:01:29,180
Now these actions corrective and preventive action and defect repair they require a change request.

19
00:01:29,180 --> 00:01:34,410
Typically you're going to have to do a change request because it's time and money that you're spending

20
00:01:36,010 --> 00:01:41,650
corrective action we're talking about current results who want to realign the project work back to our

21
00:01:41,650 --> 00:01:42,880
project plan.

22
00:01:43,180 --> 00:01:48,880
We want to make certain the work we're doing is in scope then getting rid of items that are not in scope

23
00:01:48,880 --> 00:01:55,270
so scope creep or gold plating those are not acceptable here remember scope creep as our scopes getting

24
00:01:55,270 --> 00:01:58,600
bloated by tiny changes or gold plating.

25
00:01:58,630 --> 00:02:05,520
We're just trying to consume the budget by adding bells and whistles that wasn't really approved preventive

26
00:02:05,520 --> 00:02:06,030
action.

27
00:02:06,030 --> 00:02:12,390
We want things like safety training looking for problems or risk that could happen.

28
00:02:12,390 --> 00:02:22,200
So this ties in to Chapter 11 on risk management the factory pair is we have a non-conforming product

29
00:02:22,200 --> 00:02:24,860
like those doors that weren't installed properly.

30
00:02:24,870 --> 00:02:27,280
So it kind of ties back to corrective action.

31
00:02:27,460 --> 00:02:33,000
So you want to fix the problem and then we have defect repair validation to make sure it was fix that

32
00:02:33,330 --> 00:02:35,360
when you go and fix the problem.

33
00:02:35,370 --> 00:02:40,640
Make certain that it's of quality now that it's conforming to our requirements.

34
00:02:41,540 --> 00:02:43,700
Then you have to do some updates here.

35
00:02:43,720 --> 00:02:50,370
So you may have to look at your project documentation and your plans and what updates are happened.

36
00:02:50,450 --> 00:02:56,780
So that may require a change request so changes to project documentation could be things like activity

37
00:02:56,780 --> 00:03:00,290
less because now you have activities to redo the work.

38
00:03:00,290 --> 00:03:01,780
Are there assumptions.

39
00:03:01,990 --> 00:03:03,530
What about your lessons learned.

40
00:03:03,530 --> 00:03:07,030
So you don't have to do this again and again and again.

41
00:03:07,040 --> 00:03:12,800
We're going to learn from the problems we don't have it year so corrective action and preventive action

42
00:03:12,800 --> 00:03:19,010
tie in together their requirements documentation see if the update your requirements make certain that

43
00:03:19,010 --> 00:03:23,740
everything is conforming to the requirements who want clarity on requirements.

44
00:03:23,750 --> 00:03:28,420
Are there any risk at it or stakeholder register comes into play here.

45
00:03:28,580 --> 00:03:35,560
So these are all changes that could come about because of these actions and that these formally controlled

46
00:03:35,560 --> 00:03:40,850
changes means you likely need a change request and of course you'll have updates to O.P..
