1
00:00:04,650 --> 00:00:09,650
We're still in Project integration management we've been initiating we've done planning.

2
00:00:09,810 --> 00:00:14,530
Now we're going to talk about the processes to direct and manage project work.

3
00:00:14,550 --> 00:00:18,100
We know that project management is about getting things done.

4
00:00:18,120 --> 00:00:24,150
So this means executing our process for executing is to direct and manage the project work we want the

5
00:00:24,150 --> 00:00:27,090
project team to go out and get things done.

6
00:00:27,300 --> 00:00:32,970
So this process is about satisfying project objectives doing the work spending the money.

7
00:00:33,120 --> 00:00:38,280
This is done throughout the project lifecycle so each phase we're doing the work right.

8
00:00:38,280 --> 00:00:41,950
So we're directing and managing the project work.

9
00:00:41,970 --> 00:00:48,060
It's also about managing risk and allowing approved changes to come into the project.

10
00:00:49,000 --> 00:00:53,910
So other things that you'll do in directing and managing the work we have to manage communications.

11
00:00:53,950 --> 00:00:59,710
So follow that communications management plan collecting project data that we're not just doing the

12
00:00:59,710 --> 00:01:00,360
work.

13
00:01:00,430 --> 00:01:03,160
We also need some data about the work.

14
00:01:03,160 --> 00:01:09,040
So things about actual cost versus what was plain and actual duration of task.

15
00:01:09,250 --> 00:01:15,380
What's the overall project progress and then that allows us to report on that business.

16
00:01:15,400 --> 00:01:21,110
So we'll talk about data a little bit more detail coming up completing lessons learned.

17
00:01:21,130 --> 00:01:28,120
We do this throughout the project and managing stakeholder engagement we want stakeholders engaged and

18
00:01:28,120 --> 00:01:33,740
then we also want to increase their engagement or maintain their engagement.

19
00:01:33,740 --> 00:01:41,440
Let's look at the Ito's for direct and manage project work for inputs here the PM plan any part of the

20
00:01:41,740 --> 00:01:46,390
plan can be used with directing managing work the different project documents.

21
00:01:46,390 --> 00:01:54,070
Well specifically the change log are lessons learned milestones list or communications the schedule

22
00:01:54,460 --> 00:01:57,840
a new term requirements traceability matrix.

23
00:01:57,940 --> 00:02:02,260
This is a table where we just track requirements through the project.

24
00:02:02,710 --> 00:02:07,480
We're really going to see that in chapter 5 on Scope management requirements.

25
00:02:07,750 --> 00:02:10,650
The risk register Risk Report.

26
00:02:10,750 --> 00:02:13,180
So those are all project documents.

27
00:02:13,180 --> 00:02:18,640
The approved change requests we have to get those into the project to actually create them and then

28
00:02:18,640 --> 00:02:24,510
we have ECF and OPM tools and techniques you need expert judgment.

29
00:02:24,730 --> 00:02:32,900
You'll be using a project management information system APM I as like Microsoft Project are Primavera.

30
00:02:33,070 --> 00:02:38,520
That's a p.m.-I us and of course you'll have meetings with your project team outputs.

31
00:02:38,650 --> 00:02:43,660
What do you create as a result of directing and managing the work we have your deliverables.

32
00:02:43,750 --> 00:02:53,320
You'll create data that raúl data issue log change request updates to your plan into project documents

33
00:02:53,590 --> 00:02:58,780
look at all these documents that are updated here your activity list could be updated your assumptions

34
00:02:58,780 --> 00:02:59,480
log.

35
00:02:59,620 --> 00:03:02,980
Obviously lessons learned you do that throughout the project.

36
00:03:03,040 --> 00:03:05,190
Your requirements could be updated.

37
00:03:05,410 --> 00:03:08,620
Your risk register and your stakeholder register.

38
00:03:08,770 --> 00:03:15,850
These all mean that it could be updated doesn't mean they have to be and then you have a organizational

39
00:03:16,120 --> 00:03:18,410
process assets updates.

40
00:03:18,490 --> 00:03:21,430
So that's directing in managing the project work.

41
00:03:21,430 --> 00:03:29,740
Remember we're in Project integration management so this is the big process and execution about getting

42
00:03:29,740 --> 00:03:30,650
things done.